Analysis and Evaluation of Mechanized Greenhouse Construction Project using CPM Methods
Nasim Monjezi, Mohammad Javad Sheikhdavoodi, Hadi Basirzadeh and Hassan Zakidizaji
Corresponding Author: Nasim Monjezi
Submitted: December 30, 2011
Accepted: January 25, 2012
Published: September 15, 2012 |
Abstract:
|
In this study, the application of project scheduling for analysis and evaluation of mechanized
greenhouse construction project was studied using Critical Path Method (CPM) with WinQsb software. This
study was conducted in Khuzestan province of Iran. The results showed that the minimum completion time of
this project, based on using CPM method, normal time and crash time is 201 and 137 days, respectively.
Normal cost and crash cost are 3102665000 and 3187740000 Rials, respectively. Also cost slope in CPM
method is 1329300 Rials that it means cost of reducing one day of the project completion time is 1329300 Rials.
So results of CPM method showed that the cost of reducing the project completion time, to 180 days is 1600000
Rials.
Key words: CPM method, mechanized greenhouse construction, project scheduling, , , ,
|
Abstract
|
PDF
|
HTML |
|
Cite this Reference:
Nasim Monjezi, Mohammad Javad Sheikhdavoodi, Hadi Basirzadeh and Hassan Zakidizaji, . Analysis and Evaluation of Mechanized Greenhouse Construction Project using CPM Methods. Research Journal of Applied Sciences, Engineering and Technology, (18): 3267-3273.
|
|
|
|
|
ISSN (Online): 2040-7467
ISSN (Print): 2040-7459 |
|
Information |
|
|
|
Sales & Services |
|
|
|